Changes to connection charges and network access
Ofgem published its Access and Forward-Looking Charges Significant Code Review (the Access SCR) in May 2022, with the aim of reforming how certain parties access the network and how much they will contribute towards the cost of reinforcing the network to enable their connection.
The changes which come into effect for applications received from 1 April 2023, means that in most cases, customers applying for a Demand Connection will no longer have to pay towards the network reinforcement costs for their connection, while customers applying for a Generation Connection will only have to pay a proportion of the cost. All customers will still have to pay for the work to deliver the connection, known as sole-use or extension assets.